A building subcontractor submitted a bid for construction of a portion of a high-rise office building. The bid contained material computational errors. The general contractor accepted the bid with knowledge of the errors. Which of the following statements best represents the subcontractor's liability?
a. Not liable because the contractor knew of the errors.
b. Liable because the errors were unilateral.
c. Liable because the errors were material.
d. Not liable because the errors were a result of gross negligence.
Explanation
Choice "a" is correct. Unilateral mistake is a defense to a contract if the nonmistaken party knew or should have known of the mistake. Here, the contractor knew of the error.
Choice "d" is incorrect. Whether the mistake was due to ordinary negligence or gross negligence is irrelevant in determining whether the mistake will constitute a contract defense.
Choice "b" is incorrect. Unilateral mistake is a defense to a contract if the nonmistaken party knew or should have known of the mistake.
Choice "c" is incorrect. While mistake is grounds for a defense only if the mistake is material, materiality is not all that is necessary. When the mistake is unilateral, as it is here, the nonmistaken party must also have known of the mistake (or had cause to know of the mistake).
安卓版本:8.7.50 蘋果版本:8.7.50
開發(fā)者:北京正保會計科技有限公司
應(yīng)用涉及權(quán)限:查看權(quán)限>
APP隱私政策:查看政策>
HD版本上線:點擊下載>
官方公眾號
微信掃一掃
官方視頻號
微信掃一掃
官方抖音號
抖音掃一掃
Copyright © 2000 - jnjuyue.cn All Rights Reserved. 北京正保會計科技有限公司 版權(quán)所有
京B2-20200959 京ICP備20012371號-7 出版物經(jīng)營許可證 京公網(wǎng)安備 11010802044457號