Volt Co generates and sells electricity. It operates two types of power station: nuclear and wind.

The costs and output of the two types of power station are detailed below:

Nuclear station

A nuclear station can generate 9,000 gigawatts of electricity in each of its 40 years of useful life. Operating costs are $486m 

per year. Operating costs include a provision for depreciation of $175m per year to recover the $7,000m cost of building 

the power station.

Each nuclear station has an estimated decommissioning cost of $12,000m at the end of its life. The decommissioning cost relates to the cost of safely disposing of spent nuclear fuel.

Wind station

A wind station can generate 1,750 gigawatts of electricity per year. It has a life-cycle cost of $55,000 per gigawatt and an 

average operating cost of $40,000 per gigawatt over its 20-year life.

16 What is the life-cycle cost per gigawatt of the nuclear station (to the nearest $’000)?

A $54,000

B $73,000

C $87,000

D $107,000

17 Which of the following will decrease the total life-cycle cost of a nuclear station?

(1) Increasing the useful life of the station

(2) Reducing the decommissioning cost

A 1 only

B 2 only

C Both 1 and 2

D Neither 1 nor 2

18 How would the disposal cost of spent nuclear fuel be categorised in environmental management accounting (EMA)?

A A prevention cost

B A detection cost

C An internal failure cost

D An external failure cost

19 If Volt Co sets a price to earn an operating margin of 40% over the life of a wind station, what will be the total lifetime profit per station (to the nearest $m)?

A $35m

B $408m

C $560m

D $933m

20 Which of the following are benefits of life-cycle costing for Volt Co?

(1) It facilitates the designing out of costs at the product development stage

(2) It can encourage better control of operating costs over the life cycle

(3) It gives a better understanding of the causes of overhead costs

(4) It provides useful data for short-term decision-making

A 1, 2 and 3

B 1 and 2 only

C 1 and 4

D 2, 3 and 4

前往ACCA學(xué)習(xí)專區(qū)下載歷年試題及答案解析>>

為了幫助備考ACCA考試的小伙伴們高效學(xué)習(xí),正保會(huì)計(jì)網(wǎng)校為大家提供諸多班次以及專業(yè)師資,幫助大家盡早拿下ACCA:

點(diǎn)擊查看2021年ACCA新課,早買更優(yōu)惠>>

免費(fèi)試聽(tīng)

限時(shí)免費(fèi)資料

  • 近10年A考匯總

    歷年樣卷

  • 最新官方考試大綱

    考試大綱

  • 各科目專業(yè)詞匯表

    詞匯表

  • ACCA考試報(bào)考指南

    報(bào)考指南

  • ACCA考官文章分享

    考官文章

  • 往年考前串講直播

    思維導(dǎo)圖

回到頂部
折疊
網(wǎng)站地圖

Copyright © 2000 - jnjuyue.cn All Rights Reserved. 北京正保會(huì)計(jì)科技有限公司 版權(quán)所有

京B2-20200959 京ICP備20012371號(hào)-7 出版物經(jīng)營(yíng)許可證 京公網(wǎng)安備 11010802044457號(hào)